Meridian Law — Website Launch

Critical

Launch the practice-area site rebuild before the firm's rebrand announcement.

Client: Meridian Law Group (Alan Reyes)Deadline: Sep 9 (3 days)Team:JMSC

51% complete by estimated hours · 5 done · 7 open

Why this score

7 signals detected. Each one is measured from your project data.

Fact
  • critical

    Remaining work exceeds time left

    28 pts

    49h of open work remains but only ~29h of team capacity exists before the Sep 9 deadline - a shortfall of about 20h.

  • critical

    Waiting on the client

    15 pts

    "Partner bios — still need three" was sent 5 days ago with no reply.

  • warning

    Milestone "Launch" is 3 days out

    12 pts

    6 tasks under this milestone are still open.

  • warning

    2 tasks due soon with no owner

    10 pts

    "301 redirect map", "Partner approval on bios"

  • warning

    1 task blocked

    8 pts

    "Partner approval on bios" - Three partners have not returned approved bio copy

  • warning

    1 task blocked by unfinished upstream work

    5 pts

    "Final QA + launch" is due soon but waits on "Practice area pages build (8)" and "Attorney bio pages (11)"

  • warning

    1 team member over capacity

    5 pts

    Jake Morrison is at 192% (69h assigned vs 36h capacity)

Tasks

12 total

  • Blocked

    Partner approval on bios

    Three partners have not returned approved bio copy

    UnassignedSep 6
  • In progress

    Practice area pages build (8)

    JMSep 7
  • To do

    Attorney bio pages (11)

    JMSep 8
  • To do

    Design QA pass

    SCSep 8
  • To do

    Case results database

    JMSep 8
  • To do

    301 redirect map

    UnassignedSep 8
  • To do

    Final QA + launch

    JMSep 9
  • Done

    Site architecture + practice area map

    JMJul 28
  • Done

    Homepage + interior page design

    SCAug 7
  • Done

    Design system

    SCAug 11
  • Done

    CMS build + templates

    JMAug 19
  • Done

    Content migration plan

    JMAug 27

Milestones

  • Launch

    Sep 9

    0/6 tasks done

Recent activity

  • Jake completed 3 of 8 practice area pages

    Sep 5

  • Requested remaining partner bios from Alan

    Sep 1